OVERVIEW

  • Internal Services being installed Apartments 9 & 10
  • Sheeting underway for Apartments 9 & 10
  • Scaffold removal continues
  • Lift installation underway
  • External Balustrades complete
  • Utility connections and final commissioning to get underway

What’s Coming Up:

  • Final builders clean to apartment 9
  • External Landscaping to ground floor apartments
  • Lift installation to continue
  • Sheer, set, sand and paint apartments 9 & 10
  • Scaffold removal and construction of stair access to apartment 9

Weather:

  • 4 wet days in last month

Completion dates:

  • Expected completion date – Late May 2018

 

Sales Status:

  • Under Contract: Apartments 2,3 & 4
  • Reserved on EOI: Apartments 7 & 8

Sales Updates:

With 8 weeks left until completion, there are 3×2 bedroom apartments and 2×3 bedroom apartments remaining. Active marketing has ceased temporarily whilst 2 bedroom apartments are completed. Confidence is high that all 2 bedroom apartments will be sold prior to completion. 3 bedroom apartments are still being introduced to owner/occupier enquiry with private on-site inspections.