Current Activity:

  • The Site Overcroft and Formwork is 90% complete with formwork arriving in 2 weeks. First frame to installed and finished in the month of May

What’s Coming Up:

  • Fixtures and Fittings are being assessed with all internal and external tiles on order.

Weather Forecast:

  • We had over 8 days of wet weather in the month of April.

Sales Activity: 3 EOI’s

  • Unit 1 – $475,000
  • Unit 2 – $545,000
  • Unit 5 – $510,000

Estimated Completion date:

  • September 2018