OVERVIEW

  • Pour level 4 slab and blockwork complete
  • Framework to level 1&2 – Apartments 1,2,3,4,& 5
  • Complete services installation to level 1 – Apartments 1 & 2 complete
  • Start services install to level 2 – Apartments 3,4, & 5

What’s Coming Up:

  • Level 4 blockwork
  • Framework to level 3 – Apartments 3,4,& 5
  • Complete services installation to level 2 – Apartments 3,4 & 5
  • Fabricate and install windows to level 1 – Apartments 1 & 2
  • Start services install to level 3 – Apartments 3,4 & 5

Weather:

  • 3 wet days in last month

Completion dates:

  • Expected completion date – August 2018

Sales Status:

  • Unconditional Contracts: Apartments 1,11 & 13
  • Under contract: Apartment 3
  • Reserved on EOI: Apartment 14

Sales Updates:

No new sales transactions have transpired since the last update. Supply is still reasonable with weekly and private inspections continuing to convert enquiry into sales.