OVERVIEW :

  • All Civil and earthworks now completed
  • All unit slabs have been marked and cut
  • Plumbing and sewage pipes being installed this month in preparation for laying of slabs
  • Formwork prep underway for slab pour
  • Party wall and steel prep underway
  • Pool excavated for Unit 6
  • Slabs to be poured for Unit 5 & 6 by end of this month
  • Sales & Marketing Campaign to start mid of September
  • Completion February 2018