OVERVIEW :

  • Units 7 – 9 fully erected
  • Internal Fit-out for Units 7 – 9 underway
  • Unit 5 – 6 fully erected
  • Internal Fit-out for Unit 5 – 6 is underway
  • Slabs poured for Unit 1- 4 complete
  • All services and plumbing for Units 1 – 4  Complete
  • Ground form work for Units 3 & 4 has commenced

SALES ACTIVITY

  • Unit 6 Under Contract
  • Unit 5 Under Contract
  • Unit 7 Under Contract
  • Unit 9 Under Contract

Expected Completion Date:

  • December 2017