OVERVIEW :

  • Ground Floor framework erected Units 1 – 5
  • Level 1 framework erected on Units 1 – 5
  • Concrete poured for all Alfresco areas
  • Staircase for Unit 1-5 to be installed by end of August
  • Colour bond roofing is now up
  • Kitchens and bathroom vanities currently being constructed off site in preparation for installation
  • 2 Sales
  • Sales & Marketing Campaign to start late August
  • Expected Completion Date: December 2017