OVERVIEW :

  • BA and Civil engineering is approved
  • We have had some minor design changes to our suspended slab over the main water pipe on the left hand side of the property as the pipe is only 450mm underground.
  • We have designed a cantilever suspended slab solution for this issue not to interrupt BCC main water line.
  • Piers for the Suspended Slab will be erected by end of August
  • Suspended slab formwork to be erected thereafter
  • Installation of new fencing commences late August
  • We anticipate formwork to commence September 15th
  • Expected Completion Date: December 2017