OVERVIEW :

  • Painters are spray painting internal: Building 1
  • Plastering and gyprock complete
  • Garage doors on by end of December
  • Scaffolding removed from building 1
  • Scaffolding for building 2 due to be removed end of December
  • External painting on buildings 1 & 2 Complete
  • All fitouts now complete
  • Tilers are finalising wet areas for all units
  • Bathrooms due for completion after Christmas
  • Kitchens have been installed in Units 1,2,3 & 4