OVERVIEW :

Current/completed works:

  • Curved driveway to basement being poured
  • Pedestrian access stairs to basement poured
  • Structural beams that support the original house have been formed and poured
  • Internal tiling and carpentry underway

What’s coming up?

  • House to be relocated early 2018
  • Construction begins on top floor apartments
  • Joinery/Cabinetry to be installed into lower 8 apartments
  • Floor Coverings installed throughout
  • Internal painting begins early Jan 2018

Sales Status:

  • Apartments : 2,4,7 and 8 – Under contract
  • Apartments 9 and 10 – Reserved under expression of interest (EOI)
  • Current sales are above estimated sale price during acquisition
  • Project is on budget

Completion date – March 2018