OVERVIEW :

  • Internal works are complete
  • Internal painting to all Units are being completed in month of January.
  • Water and Sewage lines are currently being connected on right hand side of the boundary running the length of the property.
  • Landscaping to commence in month of February
  • Driveway to be poured in the month of February
  • Titles to be issued at the end of February
  • We currently have Unit 1,3,8 left to sale
  • Carpet and all internal fixtures and fittings to be completed in first second week of February
  • Returns to investors shall be coordinated once all units are sold and titles are issued

Sales Activity:

Units 2,4,5,6,7 and 9  – Under Contract

EOI Activity:Unit 3