OVERVIEW :

Current/ Completed works

  • Basement slab being poured
  • Level 1 formwork being erected
  • Level 1 structural steel being placed
  • Level 1 podium concrete pour due

What’s coming up?

  • Level blockwork installation:10/1/18
  • Level 2 formwork being erected: 15/1/18
  • Level 2 structural steel being placed: 22/1/18
  • Level 2 podium concrete pour: 31/1/18

Weather

  • 2 wet days in past 4 weeks

Completion date: July 2018

Sales Status:

  • Apartments 2 and 11 –  unconditional
  • Apartments 3 and 13 – under contract