OVERVIEW :

  • Project 95 % complete
  • Tiling complete inside and outside
  • Shower screens and bathroom fittings installed
  • Painters are finalising touch ups
  • Staircases now prepared & oiled
  • Landscaping completed by end of December
  • Final clean 50% done with completion end of December
  • All electrical complete
  • Energex booked for final completion
  • Kitchens now complete with installation of ovens and dishwashers
  • Hot water systems in
  • Letter boxes due for completion end of December
  • Current sales are above estimated sale price during acquisition
  • Project is on budget

Sales Activity:

  • Unit 3 – Under Contract $645,000

 Expression of Interest (EOI) 

  • Unit 5 – $615,000