OVERVIEW :

  • Driveway is now 50% complete
  • Plan Ceiling now with Town planners
  • Internal fixtures and fittings completed
  • Kitchens are 90% installed
  • All External Tiling & Paint work is completed
  • Landscaping to commence end of February
  • Project Construction Completion Date: March 15th 2018
  • Current Sales are above estimated sale price during acquisition
  • Project is on Budget

SALES STATUS

Strong interest from Marketing Activity with Open Homes now being held most weekends

Sales Status

Under Contract

  • Unit 6 – $632,000
  • Unit 7 – $628,000
  • Unit 1 – $525,000

Expression of Interest

  • Unit 3 – $528,000
  • Unit 8 – $620,000
  • All External Paint work is completed
  • Landscaping to commence in month of February
  • NBN and Tele commutation diagram submitted to the NBN for certification
  • Project Construction Completion Date: March 15 th 2018