OVERVIEW :

Current /Completed Works

  • All joinery has been installed in lower 8 apartments
  • Roof trusses have been installed and roof has been installed
  • Floor coverings in all 2 bedroom apartments have been laid
  • Shower screens wardrobes and tiling complete to all wet areas
  • Balustrade to all rear facing apartments
  • Scaffold removal underway
  • Final certification process has begun

What’s coming Up

  • Internal services being installed to Apartments 9 & 10
  • Scaffold removal to continue
  • Lift installation in 2 weeks
  • Sheet, set and paint apartments 9 & 10
  • Utility connections and final commissioning to get underway

Sales Activity:

  • Apartment 2: Under Contract
  • Apartment 3: Under Contract
  • Apartment 4: Under Contract
  • Apartment 7: Under EOI
  • Apartment 8: Under EOI

Marketing :

With 8 weeks left until completion we have 3×2 bedroomed apartments and the 2 x 3 bedroom apartments remaining. Active marketing has ceased temporarily while we complete the 2 bedroom apartments however we are still confident of having all 2 bedroom apartments sold prior to completion. As construction progresses on the 3 bedroom apartments we continue to introduce the owner/occupier enquiry to these apartments with private site inspections.

Weather Report:

  • 6 “wet” days in past month

Expected Completion Date:

  • May 2018