OVERVIEW

  • Preparation and footings for the **undercroft currently being poured.
  • Back Half of undercroft is complete
  • Front part complete by end of Feb
  • Sewerage & main water pipes have been diverted as per development approval
  • Driveway to be erected during month of Feb with framework construction to commence month of March

** undercroft is the supporting slab which forms the foundation for the townhouses to sit on.