OVERVIEW :

  • Level 1 blockwork installation
  • Level 2 formwork being erected
  • Level 2 structural steel being placed
  • Level 2 podium concrete pour
  • Level 3 Slab pour complete

What’s coming up:

  • Level 2 Form up and pour lift shaft and verticals due 22/2
  • Level 2 Blockwork and corefill due 23/2
  • Level 3 Formwork being erected due 1/3
  • Level 3 Structural steel being placed 8/3

Weather Report:

  • 6 “wet days in last month

Sales Report:

  • Apartments 2 & 11 – Unconditional Contracts
  • Apartments 3 and 13 – Under Contract

Property transactions have been frustratingly slow throughout January but enquiry is still strong and working with 4 qualified buyers to get them to contract. Have had some interest enquiry on the back of some positive news around Queensland property

Expected Completion Date:

  • July 2018