Brisbane City Council has requested an amendment to new stormwater drains and locations for the new plans which were submitted on the 12th of March 2018. We have engaged our Civil Engineers to perform this work and these supporting documentation will be available by 5th May. We then submit these new stormwater designs to the BCC completing their last requirements.

What’s Coming Up:

  • We are expecting the DA to be approved in the order of 45 days from this update.
  • Commencement on site after DA approval is out.

Expected Construction date:

  • July 2018