OVERVIEW :

Current/completed works:

  • Curved driveway to basement Complete
  • Pedestrian access stairs Complete
  • Structural beams that support the original house are in place and house in fixed in final situ
  • Internal tiling and carpentry completed on Units 2 and 4 complete

What’s coming up?

  • House has been relocated and internal carpentry has commenced
  • Construction and formwork has commenced on top floors
  • Project is on budget
  • Joinery/Cabinetry has been installed in:
    • Unit 2
    • Unit 3
    • Unit 4
    • Unit 5
  • Floor Coverings installed in month of February :
    • Unit 2
    • Unit 3
    • Unit 4
    • Unit 5
  • Internal painting has commenced and complete on the following Units:
    • Unit 2
    • Unit 3
    • Unit 4
    • Unit 5

Sales Status:

  • Apartment 2 – Under Contract
  • Apartment 4 – Under Contract
  • Apartment 8 –  Under Contract
  • Apartment 7 – Under Contract

Expression of Interest (EOI)

  • Apartment 9