OVERVIEW :

  • Work commenced back on site 15th of January 2018
  • Whilst digging out the trench to lay the sewage rock was hit
  • The trench is 60m long and runs the length of the boundary
  • We continue to dig 5m a Day at about 2m deep and we anticipate that this work should be finalised by 10th of February
  • Once Sewage has been connected, all civils will commence
  • Landscaping and Driveway preparation to commence
  • Plan Ceiling and issue of Titles will commence around end of February

Sales Activity:

  • Unit 2: Under contract
  • Unit 4: Under contract
  • Unit 5: Under contract
  • Unit 6: Under contract
  • Unit 7: Under contract
  • Unit 9: Under contract

Expression of Interest

  • Unit 3