OVERVIEW :

Marketing material printed and circulated to buyer groups.

  • Structure complete for the first 2 levels (Apartments 1-4)
  • Civil works & footings complete for carpark slab
  • Formwork for level 3 suspended slab to begin on the 26 th  July
  • Structural columns to carpark to be installed by 27th July
  • Carpark Slabs scheduled to be poured by the 31st of July.
  • Project scheduled and on target for completion by January 31st