OVERVIEW :

  • House relocation complete
  • Construction has begun on top floor apartments
  • Internal painting to commence
  • External tiling underway

What’s coming up?

  • Joinery/Cabinetry to be installed into lower 8 apartments w/c 21/2
  • Roof trusses are being fabricated and expected to be installed by end of Feb
  • Roof sheets and windows to follow truss installation
  • Floor coverings will be installed throughout once joinery installed
  • Internals mostly complete
  • Balustrade install and scaffold removal
  • Project is on Budget

Weather forecast

  • 8 “wet days” last month

Sales Status:

  • Apartment 2 – Under Contract
  • Apartment 4 – Under Contract
  • Apartment 8 –  Under Contract
  • Apartment 7 – Under Contract

Expression of Interest (EOI)

  • Apartment 9
  • Apartment 10

With 8 weeks remaining until completion we have 2×2 and 2×3 bedroom apartments remaining. Enquiry is still consistent and confident that all 2 bed apartments will be sold prior to completion. As construction progresses on the 3 bed apartments introduction will commence to owner occupier enquiry  with site inspections over the coming weeks.

Expected completion date:

  • April 2018