OVERVIEW :

  • All exterior work now 80% complete
  • Internal painting complete
  • Kitchens presently being installed
  • Tiling has commenced
  • Wooden flooring installation has commenced
  • Balconies now enclosed with tiling being prepared for grouting
  • Painting to Balcony Ceilings scheduled on completion of grouting
  • Communal Area being prepared
  • Landscaping preparation has commenced
  • Poolworks ongoing
  • Aircon due to be installed early to mid April

Sales Activity:

  • Contract on Unit 1

Marketing :

  • Ongoing online marketing with Domain
  • Open Homes on enquiry demand

Weather Report:

  • Several days lost to inclement weather in and around Brisbane

Expected Completion Date:

  • End of April

Expected Titles Issue Date:

  • Late April/Early May