OVERVIEW

  • Footings for the *ündercroft have been completed
  • Concrete to be poured early April
  • Driveway to be poured mid April
  • Framework for Level 1 to commence mid april
  • All prefab formark is being completed offsite

Weather Forecast:

  • Several days lost to inclement weather throughout the Brisbane region

*undercroft is the supporting slab which forms the foundation for the townhouses to sit on