OVERVIEW :

  • Rain delays have been experienced
  • Civils are now complete with stormwater completed
  • Front of project entry walls now complete
  • Driveways are now being prepared for concrete pour 29/3
  • Boundary fencing has been erected
  • Exterior painting complete
  • Landscaping due for completion mid April
  • Kitchens, laundry, bathrooms and ensuites complete
  • All timber flooring has been installed
  • Carpets due to be laid early to mid April

Sales Activity:

  • Units: 1.2,3,4, 5,7,8 & 9 Under Contract
  • Unit 6: Last available remaining Unit

Marketing :

  • Online marketing with Domain
  • Weekend and midweek open homes

Expected Completion Date:

  • April

Expected Titles Issue Date:

  • April