OVERVIEW :

Current /Completed Works

  • Framing to Level 1 Apartments 1&2
  • Stripping to Level 2 form work
  • Poured Level 3 slab
  • Blockwork and corefill complete to Level 3
  • Basement services installed

What’s coming Up

  • Pour Level 4 slab and blockworks
  • Framework to Level 2  – Apartments 3,4 & 5
  • Complete services installation to Level 1 – Apartments 1 & 2
  • Fabricate and install windows to Level 1 – Apartments 1 & 2
  • Start services install to Level 2 – Apartments 3,4 & 5

Sales Activity:

  • Apartment 2: Unconditional
  • Apartment 3: Under Contract
  • Apartment 11: Unconditional
  • Apartment 13: Unconditional
  • Apartment 14: Under EOI

Marketing :

Property transactions and enquiry have picked up  with 5 new leads from Easter period alone and an EOI submitted on the Penthouse Apartment. Weekly and private inspections are continuing over the coming weeks to convert enquiry to sales.

Weather Report:

  • 8 “wet” days in past month

Expected Completion Date:

  • August 2018