OVERVIEW :

Current & Completed Works

  • Structure complete on all residential levels
  • House relocated into temporary position on top of level 4 structural slab
  • Driveway and basement excavation complete
  • Sheeting and setting complete on lower 2 levels

What’s coming up?

  • Footing and retaining for driveway ramp and remainder of basement
  • Formwork for structural beams to support original house
  • Curved blockwork
  • Sheeting and setting to remaining apartments
  • Fit off to internal carpentry (skirtings and architraves to windows and doors)

Weather report:

  • 3 “wet days” in the past month

Completion date

  • Expected completion date – February 2018

Total Apartments: 10 – Sales Activity/Update:

  • Apartment 2 – Under Contract
  • Apartment 4 – Under Contract
  • Apartment 8 –  Contract Issued
  • Apartment 9 –  Reserved with EOI
  • Apartment 10 – Reserved with EOI

Tier 1 Sales Group converted enquiry on Lots 4&8 and currently have buyers considering Lots 1&3 and expect confirmation prior to Christmas. A local strategy is being initiated with relaestate.com.au to close out the balance of stock and may entice any investment groups to commit their buyers to the properties being accessible to the general public. This campaign will run through December/January periods.