OVERVIEW :

  • Roof is now complete
  • External cladding commenced
  • Cladding due for completion approx 3 weeks
  • Level 2 framework complete
  • All blockwork for pool and retention walls are ready to go
  • Trusses on and complete
  • Plumbing re piping and electrical first fix complete
  • Top floor windows installed
  • Waterproofing decks to commence w/c 27/11
  • Insulation to be installed first week of December
  • Internal gyprock sheeting to commence in approximately 3 weeks