OVERVIEW :

  • Scaffolding removed
  • Internal painting has commenced
  • Waterproofing complete in bathrooms and showers
  • Floor and wall tiling in bathrooms/ensuites has commenced
  • Bathroom vanities currently being installed
  • Bathroom shower heads and tapware currently being installed
  • Skirting and architraves now being installed
  • Garage doors due to be installed within 7 days
  • Internal lighting being prepared for installation
  • Eaves under construction
  • Rooftop TV Aerials installed

*Does not include appliances, shower heads or tapware

Total Units: 9  Sales Activity:

  • Unit 2: Under contract
  • Unit 4: Under contract
  • Unit 5: Under contract
  • Unit 6: Under contract
  • Unit 7: Under contract
  • Unit 9: Under contract