OVERVIEW :

  • First 3 levels now complete
  • Level 4 suspended slab complete
  • Internal framing soon to commence on all 2 bdrm units
  • Windows and doors being installed on lower levels
  • Internal electrical and plumbing underway
  • Queenslander house is to be relocated to allow front of site substructural to commence

Sales Activity to date:

  • 2 sales
  • 4-5 interested parties on lots 1,3,4 and 8

Expected Completion date: February 2018