OVERVIEW :

  • Trusses to go up this week
  • Framework complete for ground and first floors
  • Party Walls complete
  • Level 2 Framework to be completed by end of October, early November
  • Blockwork, poolwork and retention walls due to commence in 10 days
  • Plumbing and electrical work due to commence end of October