ESTIMATED COMPLETION DATE – APRIL 2018

JUNE 2017

OVERVIEW :

  • Preparation for 26 Footings done
  • Negotiations are ongoing with the council relating to the placement of driveway after which time the BA will be approved
  • Structural engineers have been engaged for site preparation

JULY 2017

OVERVIEW :

  • Council approved the stage 1 BA
  • Council approved tree removals for all trees
  • Council approved relocation of main water pipe on left hand boundary
  • Council approved relocation of drive way

AUGUST 2017

OVERVIEW :

  • BA and Civil engineering is approved
  • We have had some minor design changes to our suspended slab over the main water pipe on the left hand side of the property as the pipe is only 450mm underground.
  • We have designed a cantilever suspended slab solution for this issue not to interrupt BCC main water line.
  • Piers for the Suspended Slab will be erected by end of August
  • Suspended slab formwork to be erected thereafter
  • Installation of new fencing commences late August
  • We anticipate formwork to commence September 15th
  • Expected Completion Date: December 2017

SEPTEMBER 2017

OVERVIEW :

  • Engineering and Plumbing certification approved
  • BA has been approved
  • Piers to support overcroft are being bored and installed
  • Completion Date:  April 2018

OCTOBER 2017

OVERVIEW

BCCC has approved the Civils and “ Build over Sewer” permit

  • Queensland Urban Utilities have approved the submission
  • Contractors are preparing civils for Undercroft, the platform will support the development of 5 townhouses.
  • development off the ground in accordance to the overland flooding.
  • Builders to commence on hydraulic engineering over month of November
  • 3 Presales

Click To Open/Download Document

NOVEMBER 2017

OVERVIEW

  • Earthworks approval in place
  • Stormwater approval in place
  • Minor earthworks for piers supporting overcroft completed
  • Fixtures and Fittings ordered
  • Slab for formwork to commence in early 2018
  • Civils and Construction has commenced
  • 3 Presales

Click To Open/Download Document

DECEMBER 2017

OVERVIEW

  • Footing preparation has commenced
  • Concreting of footings is scheduled to be done prior to end of December
  • All services are connected
  • Formwork and Overcroft preparation for concrete completed
  • Civil work completed
  • Reinforced steel and pillars have been delivered to site and will be installed during the month of January
  • Stormwater pipes have been fixed and connected

JANUARY 2018

OVERVIEW

  • Footing preparation has commenced
  • Concreting of footings has commenced and nearly complete
  • All services are connected
  • Formwork and Overcroft being prepared
  • Civil work completed
  • Reinforced steel and pillars have been delivered to site and installed
  • Stormwater pipes have been fixed and connected

FEBRUARY 2018

OVERVIEW

  • Preparation and footings for the **undercroft currently being poured.
  • Back Half of undercroft is complete
  • Front part complete by end of Feb
  • Sewerage & main water pipes have been diverted as per development approval
  • Driveway to be erected during month of Feb with framework construction to commence month of March

** undercroft is the supporting slab which forms the foundation for the townhouses to sit on.

MARCH 2018

OVERVIEW

  • Footings for the *ündercroft have been completed
  • Concrete to be poured early April
  • Driveway to be poured mid April
  • Framework for Level 1 to commence mid april
  • All prefab formark is being completed offsite

Weather Forecast:

  • Several days lost to inclement weather throughout the Brisbane region

*undercroft is the supporting slab which forms the foundation for the townhouses to sit on

APRIL 2018

Current Activity:

  • The Site Overcroft and Formwork is 90% complete with formwork arriving in 2 weeks. First frame to installed and finished in the month of May

What’s Coming Up:

  • Fixtures and Fittings are being assessed with all internal and external tiles on order.

Weather Forecast:

  • We had over 8 days of wet weather in the month of April.

Sales Activity: 3 EOI’s

  • Unit 1 – $475,000
  • Unit 2 – $545,000
  • Unit 5 – $510,000

Estimated Completion date:

  • September 2018

MAY 2018