ESTIMATED COMPLETION DATE – JUNE 2018

SEPTEMBER 2017

OVERWIEW :

  • Engineering and Plumbing certification approved
  • BA has been Approved
  • Civil and Earthworks to commence in October
  • 3 sales, 3 remaining
  • Completion Date April 2018

Click To Open / Download the Document

OCTOBER 2017

OVERVIEW :

  • Logan City Council have approved all BA and operational work
  • Building work to commence in the month of January 2018
  • New floor plans and design have been implemented to expand the downstairs living area
  • 2 Presales

 

NOVEMBER 2017

OVERVIEW :

  • Certificate of Supply from Energex has been granted
  • Civil and Structural documentation complete
  • New Plans for extended living and dinning area
  • 2 Contracts
  • 1 EOI ( Expression of Interest )

 

DECEMBER 2017

OVERVIEW :

  •  Subdivision documentation has been submitted to Logan City Council
  • Water and Sewage lines are currently being connected
  • Community Title Scheme is complete and awaiting approval with Council
  • Revised DA proposal attached
  • Construction to commence in month of March 2018

 

Sales Status
Under Contract

  • Unit 12
  • Unit 13
  • Unit 14

JANUARY 2018

OVERVIEW :

  • Updated Stage 2 Disclosure Statement Attached
  • Sewage pipe and excavation work on Stage 1 to Stage 2 connection currently underway
  • Energex and water mains connected to site from Stage 1
  • Subdivision and approval Documents attached
  • Commenced Civils between Stage 1 and Stage 2

SALES ACTIVITY

Contract of Sale

  • Unit 13 – $425,000
  • Unit 10 – $420,000
  • Unit 11 – $4250,000
  • Unit 12 – $ 420,000

Click To Open / Download the Document

FEBRUARY 2018

MARCH 2018

OVERVIEW

  • First Stage complete, with earthworks and civils underway

Sales Activity:

  • 4 Contracts
  • 2 EOI’s

Marketing :

  • Domain and Realestate.com.au

Weather Report:

  • 6 days of wet weather over the month of April, which has put our earthworks, construction program is behind by 26 days.

Expected Completion Date:

  • September 2018

Expected Titles Issue Date:

  • September 2018

APRIL 2018

OVERVIEW

Current

  • First Stage complete, with earthworks and civils underway

Sales Activity:

  • 4 Contracts
  • 2 EOI’s

Marketing :

  • Domain and Realestate.com.au

Weather Report:

  • 6 days of wet weather over the month of April, which has put our earthworks, construction program is behind by 26 days.

Expected Completion Date:

  • September 2018

Expected Titles Issue Date:

  • September 2018

MAY 2018