OVERVIEW :

  • Basement Carpark Complete
  • House Will Be Removed To Temporary New Position
  • Ground Floor Block Work Due to Commence
  • Framework Due for Commencement
  • Top 2 Units Under Construction
  • Units 1 & 2  Plumbing installed
  • Units 3 & 4 Stripping from Formwork from Slab in progress
  • Completion Date:  On Time

SALES ACTIVITY:

  • 2 Expression of Interest Received

 